Free tool

Plant shutdown checklist

A plant shutdown runs in six phases: plan 4 to 12 weeks out, brief everyone the week before, isolate on the day, control permits and shift changes during the work, restart in a fixed order, and debrief within a week. Fill in the checklist below, then download it as a PDF (filled or blank) or an Excel file. It includes the daily end-of-shift shutdown as a short section further down. Morsa tracks each phase’s tasks against the date and chases what is late.

Updated November 12, 2026

Shutdown and who did it
Optional
Optional
Plan: 4 to 12 weeks out (10)
1.Freeze the scope: every job on the list has a written scope, a duration and an owner
Freeze the scope: every job on the list has a written scope, a duration and an owner
2.Review open work orders and deferred maintenance; add what has been waiting for an outage
Review open work orders and deferred maintenance; add what has been waiting for an outage
3.Set the finish time before the start time, and name who can call the point of no return
Set the finish time before the start time, and name who can call the point of no return
4.Write the predecessor against every job so the critical path is visible
Write the predecessor against every job so the critical path is visible
5.List every energy source by type, size and location for each machine to be isolated
List every energy source by type, size and location for each machine to be isolated
6.List the permit-required confined spaces and the planned entries
List the permit-required confined spaces and the planned entries
7.Confirm each contractor's qualifications, insurance and scope
Confirm each contractor's qualifications, insurance and scope
8.Order long-lead parts and confirm they will be on site before the stop
Order long-lead parts and confirm they will be on site before the stop
9.Read the last shutdown's lessons learned and deviation reports
Read the last shutdown's lessons learned and deviation reports
10.Confirm the arc flash assessment is current
Confirm the arc flash assessment is current
0 of 10 marked
Your own tasks (0)

Add tasks your site needs. They print with this checklist, on the full schedule and in Excel. 0 on this checklist, 0 of 15 used across the plant shutdown checklists.

Before you file it: 3 to fix
  • FixAdd the shutdown name, so the check is filed against the right shutdown.
  • FixAdd the technician's name.
  • FixAdd the date.
  • Check10 of 10 checks are not marked yet.
Show
Plant shutdown checklistPlan: 4 to 12 weeks outPlanned shutdown or turnaround, six phases. Your site's lockout and permit procedures override this list.Shutdown nameLocationDateTechnicianCompany or siteReviewed byMark each check Done, Issue or N/A; a check with no N/A box applies to every unit. Write what is wrong against each issue and open a work order. Sourcenumbers refer to the list at the end.#Plan: 4 to 12 weeks outSourceDoneIssueN/AReading or note1Freeze the scope: every job on the list has a written scope, a durationand an owner62Review open work orders and deferred maintenance; add what hasbeen waiting for an outage53Set the finish time before the start time, and name who can call thepoint of no return64Write the predecessor against every job so the critical path is visible65List every energy source by type, size and location for each machine tobe isolated16List the permit-required confined spaces and the planned entries57Confirm each contractor's qualifications, insurance and scope58Order long-lead parts and confirm they will be on site before the stop69Read the last shutdown's lessons learned and deviation reports510Confirm the arc flash assessment is current5Technician signatureWork orders openedReviewed by (maintenance lead)DateBased on:1. OSHA, 29 CFR 1910.147, The control of hazardous energy, osha.gov (read 12 November 2026)2. OSHA, 29 CFR 1910.146, Permit-required confined spaces, osha.gov (read 12 November 2026)3. OSHA, 29 CFR 1910.252, Welding, cutting and brazing, osha.gov (read 12 November 2026)4. OSHA, 29 CFR 1910.119, Process safety management, osha.gov (read 12 November 2026)5. MaintainX, Plant shutdown checklist: a phase-by-phase safety and coordination guide (read 12 November 2026)6. Facilio, Plant shutdown checklist template (read 12 November 2026)Plant shutdown checklist: Plan: 4 to 12 weeks out.

Next, Morsa schedules this checklist, asks the technician for it from their phone, logs the result against the asset and flags any check that is missed or fails. Open the work order template or book a demo.

Blank plant shutdown forms to print:

1 page, letter size. 0 of 10 checks marked.

Runs in your browser. Nothing you type is uploaded; the check is saved only in this browser, and the PDF and Excel files are built on your device.

Plant shutdown checklist: the six phases at a glance

PhaseWhenThe one step not to skip
Plan4 to 12 weeks outFreeze the scope and set the finish time
Week beforeLast 7 daysSwap lockout procedures with contractors and prepare permit forms
Shutdown dayDay 1Isolate, relieve stored energy, then verify before work
DuringEach shiftHand lockout over in writing; permits for entries and hot work
RestartLast dayLocks off in order; one failed check stops the restart
AfterWithin a weekDebrief, actual against plan, update the procedure

MaintainX says to start planning 4 to 12 weeks ahead depending on scope. Facilio groups preparation at 30 days, 7 days and 24 hours.

How to use the plant shutdown checklist

  1. Name the shutdown and the lead. Fill in the date and where it is.

  2. Work down the phases in order. Mark each check Done, Issue or N/A; the safety steps, like verifying isolation, cannot be marked N/A.

  3. Write what is open against any failed item, with who owns it.

  4. Download the PDF for the shutdown office or the Excel file to share with the crews.

A 5-day summer shutdown, day by day

This outline is our example, built from the phases above. It is not from a standard.

DayPhaseWhat happens
Weeks beforePlan, week beforeScope frozen, parts on site, contractors briefed, permit forms prepared
Day 1Shutdown dayStop by procedure, isolate, relieve stored energy, verify; start the first jobs
Days 2 to 4DuringTest and permit each entry and hot job, hand over locks at each shift, record planned against actual daily
Day 5RestartInspect, take locks off in order, restore utilities, test interlocks, get sign-off
Within a weekAfterClose work orders, debrief, update the procedure

Manufacturing plant shutdown: what OSHA requires on the day

OSHA 29 CFR 1910.147 covers servicing work where unexpected start-up or stored energy could injure people. Its steps, in the order the standard gives them, are the backbone of the shutdown day checklist.

StepWhat 1910.147 saysWhere it is on the checklist
PrepareKnow “the type and magnitude of the energy” and how to control itPlan, item 5: list every energy source
Shut down“An orderly shutdown must be utilized”Shutdown day, item 1
Isolate and lockOperate every isolating device; apply lockout or tagoutShutdown day, item 2
Stored energyRelieve, disconnect, restrain “or otherwise rendered safe”Shutdown day, item 3
VerifyVerify isolation before starting workShutdown day, item 4
ContractorsThe plant and the contractor “shall inform each other of their respective lockout or tagout procedures”Week before, item 2
Groups and shiftsA named authorized employee coordinates; protection continues across shift changesShutdown day, item 5; During, item 1

Permits during a plant shutdown

  • Confined spaces. 1910.146 requires testing conditions in the permit space before entry is authorized, and canceling the entry permit when the entry is over. Canceled permits are kept for at least 1 year to review the program.

  • Hot work. 1910.252 says the area is inspected before cutting or welding, preferably with a written permit. It requires a fire watch where combustibles are within 35 feet, and the watch continues “for at least a half hour” after the work.

  • Process safety plants. 1910.119(i) requires a pre-startup safety review for new facilities and significant modifications. It is not a rule for every routine restart; use it as a model if your plant is covered.

Restart: take the locks off in order

1910.147(e) sets three checks before locks come off: the work area is inspected so “nonessential items have been removed” and components are intact; everyone is checked and positioned safely; affected employees are told the locks are coming off. Each lock is removed by the person who applied it. Then start up in the planned order. Facilio’s template treats the pre-startup review as a gate where one failed check stops the restart. We do the same.

Daily plant shutdown checklist (end of shift)

A routine end-of-shift stop is not a turnaround, but the same rules apply to anything being serviced overnight.

  • Stop each machine by its own procedure; 1910.147 asks for an orderly shutdown.

  • Lock out anything that will be serviced overnight and hand the lock to the next shift in writing.

  • Clean down: OSHA 1910.22(a) requires work areas and floors to be clean, orderly and free of hazards such as leaks and spills.

  • Write open defects on the handover; see the shift handover template.

Plant shutdown mistakes

  1. Open-ended finish. A shutdown with no set finish finds more work to fill it.

  2. Unwritten scope. Late additions are what overrun the critical path.

  3. Verbal lock handovers. Each shift change is a place where a lock goes missing.

  4. Skipping contractor lockout exchange. OSHA requires both sides to share their procedures.

  5. Treating restart as the easy part. Guards left off and permits left open are found here.

  6. No debrief. The lessons are only useful if written within the week.

Keeping the shutdown on schedule

Morsa turns the plan into dated tasks. It sends each owner their tasks for the week in WhatsApp, Teams, text or email, tracks completion against the plan and chases what is late. When a long-lead part is not confirmed 30 days out, it tells the shutdown lead and offers to chase the supplier from the buyer’s own mailbox once a person approves. Every skipped or failed check is listed for the lead each morning.

Other maintenance checklists

Frequently asked questions

What is a plant shutdown checklist?

A phase-by-phase list for planning, isolating, working through and restarting a plant outage. Ours has 51 checks in six phases.

How far ahead should you plan a plant shutdown?

MaintainX says 4 to 12 weeks, depending on scope. Facilio groups preparation tasks at 30 days, 7 days and 24 hours.

What is the difference between a shutdown and a turnaround?

A turnaround is a planned shutdown for maintenance, inspection and repair of a plant or unit. The checklist works for either.

Is there a shutdown checklist template in Excel?

Yes. Fill in the checklist above and download the Excel file, or print the blank PDF.

What is a facility shutdown checklist?

This checklist is written for manufacturing plants. Its OSHA lockout, permit and hot work steps apply to any workplace servicing equipment. Facilio’s template adds occupant notification for commercial buildings.

What does a daily plant shutdown checklist include?

An orderly machine stop, lockout of anything under service, housekeeping and a written handover. See the end-of-shift section above.

Where Morsa fits

Get the shutdown plan done, not just written.

Morsa turns the checklist into dated tasks, asks each owner for their part and flags what is late. It works in whatever your plant runs on: WhatsApp, Teams, email or text.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Morsa. All Rights Reserved. A Product by Lunar.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Morsa. All Rights Reserved. A Product by Lunar.