Plant shutdown checklist
A plant shutdown runs in six phases: plan 4 to 12 weeks out, brief everyone the week before, isolate on the day, control permits and shift changes during the work, restart in a fixed order, and debrief within a week. Fill in the checklist below, then download it as a PDF (filled or blank) or an Excel file. It includes the daily end-of-shift shutdown as a short section further down. Morsa tracks each phase’s tasks against the date and chases what is late.
Updated November 12, 2026
Plant shutdown checklist: the six phases at a glance
| Phase | When | The one step not to skip |
|---|---|---|
| Plan | 4 to 12 weeks out | Freeze the scope and set the finish time |
| Week before | Last 7 days | Swap lockout procedures with contractors and prepare permit forms |
| Shutdown day | Day 1 | Isolate, relieve stored energy, then verify before work |
| During | Each shift | Hand lockout over in writing; permits for entries and hot work |
| Restart | Last day | Locks off in order; one failed check stops the restart |
| After | Within a week | Debrief, actual against plan, update the procedure |
MaintainX says to start planning 4 to 12 weeks ahead depending on scope. Facilio groups preparation at 30 days, 7 days and 24 hours.
How to use the plant shutdown checklist
Name the shutdown and the lead. Fill in the date and where it is.
Work down the phases in order. Mark each check Done, Issue or N/A; the safety steps, like verifying isolation, cannot be marked N/A.
Write what is open against any failed item, with who owns it.
Download the PDF for the shutdown office or the Excel file to share with the crews.
A 5-day summer shutdown, day by day
This outline is our example, built from the phases above. It is not from a standard.
| Day | Phase | What happens |
|---|---|---|
| Weeks before | Plan, week before | Scope frozen, parts on site, contractors briefed, permit forms prepared |
| Day 1 | Shutdown day | Stop by procedure, isolate, relieve stored energy, verify; start the first jobs |
| Days 2 to 4 | During | Test and permit each entry and hot job, hand over locks at each shift, record planned against actual daily |
| Day 5 | Restart | Inspect, take locks off in order, restore utilities, test interlocks, get sign-off |
| Within a week | After | Close work orders, debrief, update the procedure |
Manufacturing plant shutdown: what OSHA requires on the day
OSHA 29 CFR 1910.147 covers servicing work where unexpected start-up or stored energy could injure people. Its steps, in the order the standard gives them, are the backbone of the shutdown day checklist.
| Step | What 1910.147 says | Where it is on the checklist |
|---|---|---|
| Prepare | Know “the type and magnitude of the energy” and how to control it | Plan, item 5: list every energy source |
| Shut down | “An orderly shutdown must be utilized” | Shutdown day, item 1 |
| Isolate and lock | Operate every isolating device; apply lockout or tagout | Shutdown day, item 2 |
| Stored energy | Relieve, disconnect, restrain “or otherwise rendered safe” | Shutdown day, item 3 |
| Verify | Verify isolation before starting work | Shutdown day, item 4 |
| Contractors | The plant and the contractor “shall inform each other of their respective lockout or tagout procedures” | Week before, item 2 |
| Groups and shifts | A named authorized employee coordinates; protection continues across shift changes | Shutdown day, item 5; During, item 1 |
Permits during a plant shutdown
Confined spaces. 1910.146 requires testing conditions in the permit space before entry is authorized, and canceling the entry permit when the entry is over. Canceled permits are kept for at least 1 year to review the program.
Hot work. 1910.252 says the area is inspected before cutting or welding, preferably with a written permit. It requires a fire watch where combustibles are within 35 feet, and the watch continues “for at least a half hour” after the work.
Process safety plants. 1910.119(i) requires a pre-startup safety review for new facilities and significant modifications. It is not a rule for every routine restart; use it as a model if your plant is covered.
Restart: take the locks off in order
1910.147(e) sets three checks before locks come off: the work area is inspected so “nonessential items have been removed” and components are intact; everyone is checked and positioned safely; affected employees are told the locks are coming off. Each lock is removed by the person who applied it. Then start up in the planned order. Facilio’s template treats the pre-startup review as a gate where one failed check stops the restart. We do the same.
Daily plant shutdown checklist (end of shift)
A routine end-of-shift stop is not a turnaround, but the same rules apply to anything being serviced overnight.
Stop each machine by its own procedure; 1910.147 asks for an orderly shutdown.
Lock out anything that will be serviced overnight and hand the lock to the next shift in writing.
Clean down: OSHA 1910.22(a) requires work areas and floors to be clean, orderly and free of hazards such as leaks and spills.
Write open defects on the handover; see the shift handover template.
Plant shutdown mistakes
Open-ended finish. A shutdown with no set finish finds more work to fill it.
Unwritten scope. Late additions are what overrun the critical path.
Verbal lock handovers. Each shift change is a place where a lock goes missing.
Skipping contractor lockout exchange. OSHA requires both sides to share their procedures.
Treating restart as the easy part. Guards left off and permits left open are found here.
No debrief. The lessons are only useful if written within the week.
Keeping the shutdown on schedule
Morsa turns the plan into dated tasks. It sends each owner their tasks for the week in WhatsApp, Teams, text or email, tracks completion against the plan and chases what is late. When a long-lead part is not confirmed 30 days out, it tells the shutdown lead and offers to chase the supplier from the buyer’s own mailbox once a person approves. Every skipped or failed check is listed for the lead each morning.
Other maintenance checklists
Preventive maintenance checklist: the hub, a general PM checklist for any machine
Chiller maintenance checklist: daily readings and annual service
Boiler maintenance checklist: steam and hot water
Generator maintenance checklist: weekly, monthly and annual tests
Air compressor maintenance checklist: drains, filters and safety valves
Frequently asked questions
What is a plant shutdown checklist?
A phase-by-phase list for planning, isolating, working through and restarting a plant outage. Ours has 51 checks in six phases.
How far ahead should you plan a plant shutdown?
MaintainX says 4 to 12 weeks, depending on scope. Facilio groups preparation tasks at 30 days, 7 days and 24 hours.
What is the difference between a shutdown and a turnaround?
A turnaround is a planned shutdown for maintenance, inspection and repair of a plant or unit. The checklist works for either.
Is there a shutdown checklist template in Excel?
Yes. Fill in the checklist above and download the Excel file, or print the blank PDF.
What is a facility shutdown checklist?
This checklist is written for manufacturing plants. Its OSHA lockout, permit and hot work steps apply to any workplace servicing equipment. Facilio’s template adds occupant notification for commercial buildings.
What does a daily plant shutdown checklist include?
An orderly machine stop, lockout of anything under service, housekeeping and a written handover. See the end-of-shift section above.
Related tools
Sources
OSHA, 29 CFR 1910.147, The control of hazardous energy, osha.gov (read November 12, 2026)
OSHA, 29 CFR 1910.146, Permit-required confined spaces, osha.gov (read November 12, 2026)
OSHA, 29 CFR 1910.252, Welding, cutting and brazing, osha.gov (read November 12, 2026)
OSHA, 29 CFR 1910.119, Process safety management, osha.gov (read November 12, 2026)
OSHA, 29 CFR 1910.22, Walking-working surfaces, osha.gov (read November 12, 2026)
MaintainX, Plant shutdown checklist (read November 12, 2026)
Facilio, Plant shutdown checklist template (read November 12, 2026)
Where Morsa fits
Get the shutdown plan done, not just written.
Morsa turns the checklist into dated tasks, asks each owner for their part and flags what is late. It works in whatever your plant runs on: WhatsApp, Teams, email or text.