Long lead items tracker for data center equipment

For energization on 2 April 2029, a 25 to 50 MVA substation transformer needed its PO by 21 September 2026 (planning on 110 weeks), and a transformer above 50 MVA by 15 December 2025. Enter your energization date and items to get the order-by, release and ship dates for each, set against the vendor’s promised date, with a flag on every item that misses or has under 8 weeks of float. The tracker opens on that 60 MW campus. Download it as Excel with live date formulas, or as a PDF; for an empty template, click Start blank and download the Excel file.

Updated November 8, 2026

Long-lead equipment tracker

This is the 60 MW campus from the lead-times guide: energization on 2 April 2029, eight items at the top of their lead-time ranges, three of them on order. Vendors and PO numbers are made up. Change any cell, or start blank.

Project
Optional
Reads as Mon 2 Apr 2029
Reads as Sun 8 Nov 2026
8 is a default; one published switchgear slip was 8 weeks
Items (8)

Lead time runs from release to manufacture (RTM), after submittals are approved; if a vendor's quote already includes submittals, set that item's submittals to 0. The on-site buffer is the time to set, terminate and test before energization. Dates take 2029-04-02, 4/2/2029 or 2 Apr 2029; a range such as 85 to 110 plans on the top.

Add from the lead-time table

2026 lead times from the guide, at the top of each range, with 8 weeks of submittals, 2 of transit and the guide's on-site buffer.

Transformer above 50 MVA (step-up or auto-transformer)100 to 150+ weeks
Substation transformer, 25 to 50 MVA85 to 110 weeks
Substation transformer, 5 to 25 MVA65 to 95 weeks
Pad-mount transformer, 0 to 5 MVA40 to 65 weeks
Switchgear, 5 or 15 kV metal-enclosed52 to 72 weeks
Switchgear, 15 or 27 kV metal-clad60 to 80 weeks
Switchgear, 38 kV78 to 104 weeks
Diesel generator, 500 to 1,000 kW32 to 48 weeks
Diesel generator, 1,500 to 2,000 kW50 to 66 weeks
Diesel generator, 2,500 to 3,500 kW62 to 82 weeks
Diesel generator, 3,500 to 4,500 kW90 to 110 weeks
Static UPS, 500 to 1,500 kVA30 to 48 weeks
Modular UPS, 2,000 kVA and up40 to 60 weeks
Automatic transfer switches24 to 40 weeks
Chillers and coolant distribution units35 to 55 weeks
Busway20 to 40 weeks
Item 1
Item 2
Item 3
Item 4
Item 5
Item 6
Item 7
Item 8
Energization at risk6.9 weeks late

2 of 8 items miss the need date. The worst, Substation transformer, 25 to 50 MVA, lands 6.9 weeks late, which moves energization from 2 Apr 2029 to 20 May 2029 unless it is recovered. 1 more has under 8 weeks of float.

Items8
Miss the need date2
Under 8 weeks of float1
On track5
Show
2. Substation transformer, 25 to 50 MVAQty 2PO date passed 6.9 weeks ago; ordered today it lands 6.9 weeks late
Latest PO
21 Sep 2026
Latest release (RTM)
16 Nov 2026
Required on site
8 Jan 2029
Expected on site (if ordered today)
25 Feb 2029
Float
-6.9 weeks
1. Transformer above 50 MVA (step-up or auto-transformer)Qty 2, Vendor A, PO-2601Misses its need date by 5 weeks
Latest PO
15 Dec 2025
Latest release (RTM)
9 Feb 2026
Required on site
8 Jan 2029
Expected on site (vendor date)
12 Feb 2029
Float
-5 weeks
Last contact 28 Oct 2026; chase due since 4 Nov 2026
3. 15 kV metal-clad switchgearQty 6 lineups, Vendor C, PO-26146 weeks of float, under 8
Latest PO
3 May 2027
Latest release (RTM)
28 Jun 2027
Required on site
22 Jan 2029
Expected on site (vendor date)
11 Dec 2028
Float
6 weeks
Last contact 30 Oct 2026; chase due since 6 Nov 2026
4. Diesel generators, 2,500 to 3,500 kWQty 12, Vendor D, PO-2618On track, 14 weeks of float
Latest PO
17 May 2027
Latest release (RTM)
12 Jul 2027
Required on site
19 Feb 2029
Expected on site (vendor date)
13 Nov 2028
Float
14 weeks
Last contact 2 Nov 2026; next chase 9 Nov 2026
5. Pad-mount transformers, up to 5 MVAQty 8Order by 16 Aug 2027, 40.1 weeks left
Latest PO
16 Aug 2027
Latest release (RTM)
11 Oct 2027
Required on site
22 Jan 2029
Expected on site (if ordered today)
16 Apr 2028
Float
40.1 weeks
6. ChillersQty 10Order by 11 Oct 2027, 48.1 weeks left
Latest PO
11 Oct 2027
Latest release (RTM)
6 Dec 2027
Required on site
8 Jan 2029
Expected on site (if ordered today)
6 Feb 2028
Float
48.1 weeks
7. Static UPS, 500 to 1,500 kVAQty 16Order by 10 Jan 2028, 61.1 weeks left
Latest PO
10 Jan 2028
Latest release (RTM)
6 Mar 2028
Required on site
19 Feb 2029
Expected on site (if ordered today)
19 Dec 2027
Float
61.1 weeks
8. BuswayQty 1 lotOrder by 24 Jan 2028, 63.1 weeks left
Latest PO
24 Jan 2028
Latest release (RTM)
20 Mar 2028
Required on site
8 Jan 2029
Expected on site (if ordered today)
24 Oct 2027
Float
63.1 weeks

Next, Morsa tracks every long-lead PO, asks each vendor for its submittal, release, test and ship dates from your own mailbox and shows which milestone a slip hits. See the lead times it plans on or book a demo.

Chase emails (8)

One per item, written for the stage it is at: a quote request with a dated factory slot for items still to buy, a request for dates on items ordered without a vendor date, a recovery request when the vendor’s date misses, and a weekly date check for the rest.

Transformer above 50 MVA (step-up or auto-transformer)
Subject: Recovery plan needed: Transformer above 50 MVA (step-up or auto-transformer) (PO-2601)

Hello,

Your promised delivery of 12 Feb 2029 is 5 weeks after we need Transformer above 50 MVA (step-up or auto-transformer) on site (8 Jan 2029) for energization of 60 MW campus, phase 1. Please tell us by return what you can do: an earlier factory slot, a partial shipment of the first units, expedited freight or a stocked alternate, and the date each would give us.

Thank you
Substation transformer, 25 to 50 MVA
Subject: Dated slot request: Substation transformer, 25 to 50 MVA, 60 MW campus, phase 1

Hello,

We need 2 x Substation transformer, 25 to 50 MVA on site at 60 MW campus, phase 1 by 8 Jan 2029, and on your quoted lead time we are already late, so we need your earliest slot. Please send a quote with a dated factory slot letter: the release to manufacture (RTM) week, the factory test week and the ship week of the last unit, and say whether your lead time runs from the PO or from approved submittals.

Thank you
15 kV metal-clad switchgear
Subject: Weekly date check: 15 kV metal-clad switchgear (PO-2614)

Hello,

Please confirm this week's dates for 15 kV metal-clad switchgear (PO-2614): submittal approval, release to manufacture (RTM), factory acceptance test, ship and delivery (now 11 Dec 2028; we need it by 22 Jan 2029). If any date has moved, tell us the new date and the reason.

Thank you
Diesel generators, 2,500 to 3,500 kW
Subject: Weekly date check: Diesel generators, 2,500 to 3,500 kW (PO-2618)

Hello,

Please confirm this week's dates for Diesel generators, 2,500 to 3,500 kW (PO-2618): submittal approval, release to manufacture (RTM), factory acceptance test, ship and delivery (now 13 Nov 2028; we need it by 19 Feb 2029). If any date has moved, tell us the new date and the reason.

Thank you
Pad-mount transformers, up to 5 MVA
Subject: Dated slot request: Pad-mount transformers, up to 5 MVA, 60 MW campus, phase 1

Hello,

We need 8 x Pad-mount transformers, up to 5 MVA on site at 60 MW campus, phase 1 by 22 Jan 2029 and plan to place the order by 16 Aug 2027. Please send a quote with a dated factory slot letter: the release to manufacture (RTM) week, the factory test week and the ship week of the last unit, and say whether your lead time runs from the PO or from approved submittals.

Thank you
Chillers
Subject: Dated slot request: Chillers, 60 MW campus, phase 1

Hello,

We need 10 x Chillers on site at 60 MW campus, phase 1 by 8 Jan 2029 and plan to place the order by 11 Oct 2027. Please send a quote with a dated factory slot letter: the release to manufacture (RTM) week, the factory test week and the ship week of the last unit, and say whether your lead time runs from the PO or from approved submittals.

Thank you
Static UPS, 500 to 1,500 kVA
Subject: Dated slot request: Static UPS, 500 to 1,500 kVA, 60 MW campus, phase 1

Hello,

We need 16 x Static UPS, 500 to 1,500 kVA on site at 60 MW campus, phase 1 by 19 Feb 2029 and plan to place the order by 10 Jan 2028. Please send a quote with a dated factory slot letter: the release to manufacture (RTM) week, the factory test week and the ship week of the last unit, and say whether your lead time runs from the PO or from approved submittals.

Thank you
Busway
Subject: Dated slot request: Busway, 60 MW campus, phase 1

Hello,

We need 1 lot x Busway on site at 60 MW campus, phase 1 by 8 Jan 2029 and plan to place the order by 24 Jan 2028. Please send a quote with a dated factory slot letter: the release to manufacture (RTM) week, the factory test week and the ship week of the last unit, and say whether your lead time runs from the PO or from approved submittals.

Thank you

The Excel file keeps every date as a live formula from the energization date in cell B4.

Runs in your browser. Nothing you type is uploaded; the tracker is saved only in this browser, and the Excel and PDF files are built on your device.

Morsa makes this free tool.

How the dates are worked out

Everything runs back from one anchor, the energization date: permanent utility power on.

  1. Required on site = energization minus the on-site buffer, the weeks to set, terminate and test the gear.

  2. Latest ship = required on site minus transit.

  3. Latest release to manufacture (RTM) = latest ship minus the lead time. RTM is the day the factory starts building, after your submittals are approved.

  4. Latest PO = latest RTM minus the submittal weeks.

  5. Expected on site = the vendor’s promised delivery; with no promise yet, the PO date plus submittals, lead time and transit; not yet ordered, today plus the same.

  6. Float = required on site minus expected on site. Below zero, the item misses its need date by that much.

Worked example: the 25 to 50 MVA transformer

The 60 MW campus energizes on Monday 2 April 2029. The substation transformer plans on 110 weeks (the top of 85 to 110), 8 weeks of submittals, 2 of transit and a 12-week on-site buffer. It is needed on site by 8 January 2029, must ship by 25 December 2028 and be released to the factory by 16 November 2026, so the latest PO date was 21 September 2026. As of 9 November 2026, ordered that day, it lands on 26 February 2029: 7 weeks after it is needed, which moves energization to 21 May 2029 unless a held factory slot or a smaller first unit recovers it. The tool works from today’s date, so on a later day these last figures grow.

Lead times the example plans on

Equipment2026 lead time, weeksOn-site buffer, weeks
Transformer above 50 MVA100 to 150+ (plan 150)12
Substation transformer, 25 to 50 MVA85 to 11012
Switchgear, 15 or 27 kV metal-clad60 to 8010
Diesel generator, 2,500 to 3,500 kW62 to 826

Terrapin (2026), as compiled with sources on the data center equipment lead times guide, which has the full table. The tool’s lead-time table carries all 16 rows, from busway to transfer switches.

Reading the flags

FlagWhat to do
Misses its need dateAsk the vendor for recovery options this week: an earlier slot, a partial first shipment, faster freight or a stocked alternate
PO date passedNot ordered and already late: ask two makers for a dated slot letter on a standard design
Under 8 weeks of floatA single slip of a few weeks makes it late; confirm dates weekly and name an alternate
Order by a dateNot ordered yet; the date is a ceiling, so place it earlier where you can
On trackConfirm the dates in writing each month

How to use it

  1. Click Start blank and set the energization date, and the as-of date if you are replaying an earlier week.

  2. Add your items from the lead-time table, or paste them from your procurement log with the columns in the tool’s order: item, quantity, vendor, PO number, then lead time, submittals, transit and on-site buffer in weeks.

  3. Check the submittal weeks. The lead time is counted from release to manufacture, after submittals. If your vendor’s quote already includes submittals, set submittals to 0 for that item.

  4. Fill in what you know per item: PO date, the vendor’s promised delivery and the last time you heard from them.

  5. Work the flags, worst float first. The tool writes a chase email for each item, worded for its stage: a dated quote request before the PO, a request for dates after it, a recovery request when the vendor’s date misses, and a weekly date check otherwise.

  6. Download the Excel file for the team. Change B4 and every date moves; the landscape PDF is for the weekly meeting.

Frequently asked questions

What are long lead items, or long lead equipment, in construction?

Equipment that takes so long to arrive that it must be ordered before the design or the contract is finished, or it sets the finish date. On a data center that is the electrical and cooling gear: transformers, switchgear, generators, UPS, chillers, transfer switches and busway. Each goes through submittals, a factory slot, a factory test and freight, so each has dates to track after the PO.

Does a quoted lead time run from the PO or from release to manufacture?

It depends on the vendor, so ask in writing. A lead time from release to manufacture (RTM) starts only once your submittal drawings are approved, which is why the tracker adds the submittal weeks in front of it. If the quote already includes submittals, set that item’s submittals to 0.

Why flag items under 8 weeks of float?

8 is a default: in one case Archdesk published, a switchgear ship date moved 8 weeks, from week 58 to week 66. An item with less float than one slip like that can miss energization. Set your own in the tool.

Does the Excel file work in Google Sheets?

Yes. Every date is a formula from the energization date in cell B4, so it recalculates in Excel, Google Sheets and LibreOffice. Type =TODAY() in B5 to keep the float current.

Where Morsa fits

Morsa asks each long-lead vendor for its dates every week and keeps this tracker current.

You approve each kind of message once; after that it goes out under that rule, and a moved date comes back marked with the milestone it hits.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.