Free tool
Cooling tower maintenance checklist
Every day, log the disinfectant residual and walk the tower. Every week, flush dead legs and test the water. Every 3 months, grease the fan bearings, flush the basin and clean the fill and drift eliminators. Change gearbox oil every 6 months or 2,500 hours. At least once a year, take the tower offline for cleaning and disinfection. These are the CDC’s Legionella controls plus the maker’s service intervals. Fill in the checklist below, then download it as a PDF (filled or blank) or an Excel file. Morsa asks for each check and flags a missed or failed one.
Updated November 12, 2026
Cooling tower maintenance schedule at a glance
| How often | What to check | Why |
|---|---|---|
| Daily | Visual walk, disinfectant residual, chemical feed, water temperature | CDC: oxidizing disinfectants need a measurable residual every day |
| Weekly | Flush dead legs, water chemistry, strainer, make-up valve, motor reading | CDC says flush at least weekly; DOE lists weekly water tests |
| Monthly | Air inlet, nozzles, basin, drift eliminators, gearbox oil level and leaks, belts | SPX Marley’s monthly column |
| Every 3 months | Fan bearings, basin flush, fill and eliminators, belt tension | BAC sets these quarterly |
| Every 6 months or 2,500 hours | Gearbox oil change (first change at 500 hours or 4 weeks) | BAC |
| Yearly | Offline cleaning and disinfection, fan pitch, finish | CDC: at least annually |
Intervals are from CDC, the Baltimore Aircoil Series 3000 manual, the SPX Marley NC schedule and the US DOE guide. Your tower’s manual overrides them.
How to use the cooling tower maintenance checklist
Enter the tower number and the fan run hours.
Work down the checklist that is due. Mark each check Done, Issue or N/A. Water and drift checks cannot be marked N/A.
Write what is wrong against any failed check, with the reading and who was told.
Download the PDF (filled or blank) for the roof, or the Excel file for the water log.
Cooling tower water treatment: the limits
Most checklists say to test the water. This table gives limits for the circulating water from Baltimore Aircoil’s Series 3000 manual. The right numbers for your tower depend on the make-up water and the metal in the system, so your water treater sets yours.
| Property | Galvanized steel | Type 304 stainless |
|---|---|---|
| pH | 6.5 to 9.0 | 6.5 to 9.2 |
| Total dissolved solids | 1,500 ppm | 2,050 ppm |
| Conductivity | 2,400 micromhos/cm | 3,300 micromhos/cm |
| Alkalinity as CaCO3 | 500 ppm | 600 ppm |
| Chlorides | 250 ppm | 300 ppm |
BAC Series 3000 manual, Table 8, Quality guidelines for circulating water. Chemically treated water; bleed alone may need more conservative limits. ppm is parts per million.
Legionella: what the CDC says to do
Know the four factors. Sediment and biofilm, temperature, water age and disinfectant residual drive Legionella growth. Run the water below the 77 to 113 F growth range where you can.
Flush dead legs weekly and keep a measurable disinfectant residual every day.
Clean offline at least annually, and before startup, when idling and after shutdown.
Run a water management program. CDC calls these programs an industry standard for large buildings under ASHRAE 188 and says a building with a cooling tower should have one for it. We did not read ASHRAE 188 or Guideline 12 themselves; the controls here come from the CDC toolkit that implements them.
Follow your state and local rules, which CDC says take precedence where they differ.
What a Legionella test result means
CDC sets no testing interval; your water management program does. For results it gives performance indicators: under 10 CFU/mL (colony forming units per milliliter) in a cooling tower means growth looks well controlled. At or above 10 CFU/mL, conditions may allow growth. A 10- to 100-fold increase means poorly controlled growth, and more than 100-fold means uncontrolled growth. CDC says the presence of any Legionella should trigger response activities: check the sample, the equipment and the records, re-evaluate the program, treat only after that, and re-test at least 48 hours after the system returns to normal. A result alone does not measure health risk.
Drift eliminators, fill, fans and gearbox
CDC recommends high-efficiency drift eliminators and keeping the tower at least 25 feet from outside air intakes. BAC says to inspect and clean the fill and its integral eliminators at least quarterly, drain and flush the basin quarterly, grease the fan shaft bearings every 3 months or 2,000 hours, and change gearbox oil every 2,500 hours or 6 months (first change at 500 hours or 4 weeks). It also says to limit the fan motor to six on-off cycles an hour.
Where the cooling tower sources disagree
SPX Marley lists belt tension monthly, BAC at least every 3 months. A trade article says test the water monthly; the DOE guide lists weekly water samples. One checklist puts Legionella testing quarterly, but CDC gives no interval and ties it to your program. We used the shorter interval where manufacturers or DOE differ, and left the Legionella interval to your water management program.
What to do when a cooling tower check fails
Lock out before service. BAC’s manual warns that fans, motors and drives must be disconnected, locked out and tagged out before anyone works near them. OSHA 29 CFR 1910.147 requires isolation and verification.
Residual low or water out of limits: follow the response in your water management program and call your water treater.
Heavy vibration or a noisy gearbox: stop the fan and inspect before restarting.
Suspected illness: the public health authority decides if there is an outbreak. CDC’s offline emergency steps include holding at least 20 ppm, then 10 ppm for 24 hours, of free oxidant. Use a water treatment professional.
Cooling tower maintenance mistakes
Treating the tower as a mechanical item only. Water is half the job.
No written log. CDC says to keep log sheets, test procedures and results on site.
Leaving a tower idle and wet. CDC says to circulate 3 times a week in short standby.
Skipping the annual offline clean.
Letting sludge build in the basin. BAC flushes quarterly.
Keeping the cooling tower checklist on schedule
Morsa sends the daily round to the operator or the water treatment vendor in WhatsApp, Teams, text or email, logs the residual and pH against the tower and keeps the weekly flush and water test dated. If a daily residual reading is missing or out of range, Morsa tells the maintenance lead the same day. Quarterly tasks come due by date or 2,000 fan hours, whichever is first; the lead approves the schedule.
Other maintenance checklists
Preventive maintenance checklist: the hub, a general PM checklist for any machine
Chiller maintenance checklist: the machine the tower cools
Commercial HVAC maintenance checklist: rooftop units and air handlers
Boiler maintenance checklist: steam and hot water
Generator maintenance checklist: weekly, monthly and annual tests
Frequently asked questions
How often should a cooling tower be maintained?
Daily and weekly water and visual checks, monthly and quarterly mechanical items, and an offline cleaning and disinfection at least yearly, per CDC.
What is on a cooling tower maintenance checklist?
Water treatment and Legionella controls, drift eliminators, fill, basin, fans, gearbox, motor and belts, with a frequency for each.
How often should cooling tower water be tested?
The DOE guide lists weekly samples for solids and chemistry, and CDC says disinfectant residual should be measurable every day.
How often should a cooling tower be cleaned?
BAC says to flush the basin and clean the fill quarterly. CDC says at least one offline cleaning and disinfection a year.
Does a cooling tower need a Legionella water management program?
CDC says a building with a cooling tower should have a program for it, and calls programs an industry standard under ASHRAE 188. Check your state and local rules.
How often should cooling tower gearbox oil be changed?
BAC: after 500 hours or 4 weeks, then every 2,500 hours or 6 months, whichever comes first. Use your manual.
Related tools
Sources
CDC, Controlling Legionella in Cooling Towers, Legionella Control Toolkit (read November 12, 2026)
CDC, Routine Testing for Legionella, Legionella Control Toolkit (read November 12, 2026)
Baltimore Aircoil Company, Series 3000 Operation and Maintenance Manual (read November 12, 2026)
SPX Cooling Technologies, Marley NC maintenance schedule (read November 12, 2026)
US DOE FEMP, O&M Best Practices Guide, Release 3.0 (read November 12, 2026)
OSHA, 29 CFR 1910.147, The control of hazardous energy, osha.gov (read November 12, 2026)