Morsa publishes this guide. Morsa is software with an AI agent that works in your ERP, email and Teams; it checks weekly load, and a person approves what goes out.
This page is about plant capacity: machines, labor and hours. It is not about IT capacity or sales capacity.
Capacity planning formula, with a worked example for a work center
Rated capacity = available time × utilization × efficiency [1]
Available time is the hours the work center can run: machines × hours per day × days (some formulas also multiply by workers) [1].
Utilization is hours actually worked ÷ available hours [1].
Efficiency is the actual rate ÷ the standard rate, so hours worked turn into standard hours of output [1].
A work center has 2 machines on one 8-hour shift, 5 days a week. Example figures are ours.
Step | Calculation | Result |
|---|---|---|
Available time | 2 × 8 × 5 | 80 hours |
Hours actually worked (90%) | 80 × 0.90 | 72 hours |
Standard hours made (95%) | 72 × 0.95 | 68.4 hours |
That is the capacity. Now the load, the standard hours the orders need next week:
Part | Units × standard hours | Hours |
|---|---|---|
Part A | 300 × 0.10 | 30 |
Part B | 190 × 0.12 | 22.8 |
Part C | 120 × 0.15 | 18 |
The load is 70.8 standard hours against 68.4 of capacity: 70.8 ÷ 68.4 = 104%. The work center is 2.4 hours short. Options: move 16 units of Part C (16 × 0.15 = 2.4 hours) to another work center or the following week; add overtime, which takes 2.4 ÷ (0.90 × 0.95) = 2.8 clock hours because only 85.5% of a clock hour becomes standard output; or tell the customer.
Overload is rarely one week. Here is the same work center over four weeks:
Week | Load, standard hours | Load vs 68.4 capacity |
|---|---|---|
1 | 70.8 | 104% |
2 | 62.0 | 91% |
3 | 75.0 | 110% |
4 | 66.0 | 96% |
Weeks 1 and 3 are over, by 2.4 and 6.6 hours; weeks 2 and 4 have 6.4 and 2.4 hours free. Move the jobs with the latest due dates into the free hours first (our suggestion). For one overloaded cell, CRP (below) is the method that applies; rough-cut is too coarse.
Definitions differ by system. Sage 100, for example, uses only an efficiency percentage on top of available hours [2]. Check how your ERP defines the two factors before comparing numbers.
Rough-cut, CRP and finite capacity
Method | What it checks | Level of detail |
|---|---|---|
Rough-cut (overall factors, capacity bills, resource profiles) | Total hours against the master schedule | Fast, high-level [3] |
Capacity requirements planning (CRP) | Load per work center from open orders, routings and run rates | Detailed [3] |
Finite capacity | A schedule that treats each work center’s hours as a hard limit | Detailed, by work center [4] |
Rough-cut is a fast check and should not be the only method when capacity is tight [3]. CRP shows which work centers are overloaded and which have room [3]. Finite capacity planning works within the limits of the resources and is usually done in advanced planning and scheduling (APS) software; see advanced planning and scheduling [4].
Capacity planning software and tools
Planning software does the same arithmetic for every work center and week, and adds three things: what-if scenarios on demand, labor and rules; bottleneck views that show where work stacks up; and data pulled from ERP, MRP and shop-floor systems [3][4]. Three levels of tool:
A spreadsheet. The production planning workbook is enough for a few work centers.
Your ERP. Most ERPs have a CRP report or a load-by-work-center view; see MRP in your ERP.
APS software. Siemens, PlanetTogether and Netstock are examples [3][4][5]. See production planning software.
How plants and distributors use capacity planning
A plant runs it weekly, as part of the monthly S&OP cycle, to decide on overtime, a second shift, outsourcing or a new quote date. A distributor applies the same idea to the warehouse: 3,000 order lines a day at 50 lines per picker hour needs 60 picker hours, which is 7.5 people for 8 hours (our example).
Common capacity planning mistakes
Using the nameplate. A machine’s rated speed is not what it makes. Use actual run rates and downtime history.
Planning at 100% load. Any breakdown or rush order puts you late. Leave room.
Counting machines only. Labor, tooling and materials limit output too [3].
Using gross hours. Remove breaks, maintenance and changeovers before multiplying.
One plan per quarter. Rerun it when the order mix changes, because the mix changes the hours per unit [1].
Ignoring the bottleneck. Adding capacity anywhere else changes nothing.
Checking load against capacity every week
Capacity plans go stale, so Morsa reruns the check:
It reads open orders, routings and work center calendars from your ERP and calculates load against rated capacity for each work center and week.
For any week over 100% it shows the orders affected and the options: overtime hours, a move to another work center, or a later promise date.
The planner approves the choice, Morsa updates the schedule in the ERP and tells the supervisors in Teams.
To see it on your work centers, book a 30-minute walkthrough.
Related terms
Operations glossary: every term.
S&OP: the monthly meeting where capacity is traded against demand.
Takt time: the pace demand sets, which capacity must meet.
Make to order vs make to stock: how stocking policy changes the load on capacity.
Lead time: what an overloaded work center does to the date you quote.
Sources
Vskills, Capacity Measurement (a training provider): https://www.vskills.in/certification/tutorial/capacity-measurement/ (read 12 November 2026)
Sage 100, Determining Work Center Capacity: https://help-sage100.na.sage.com/2023/Subsystems/PM/PMConcepts/Determine_Work_Ctr_Cap.htm (read 12 November 2026)
PlanetTogether, What Type of Capacity Planning Does Your Business Need? (an APS vendor): https://www.planettogether.com/aps-trends/what-type-of-capacity-planning-does-your-business-need (read 12 November 2026)
Siemens, Manufacturing Capacity Planning (an APS vendor): https://www.siemens.com/en-us/technology/manufacturing-capacity-planning/ (read 12 November 2026)
Netstock, Practical Capacity Planning Guide for Manufacturers (a software vendor): https://www.netstock.com/blog/practical-capacity-planning-guide-for-manufacturers/ (read 12 November 2026)