How to Get Suppliers to Confirm Ship Dates

Suppliers confirm ship dates when confirmation is part of the deal, not a favor you ask for. Write a confirm-by deadline into your PO terms, ask for a ship date on every line, make replying take one click or one line, require reconfirmation whenever the order changes, and score each supplier on acknowledgment and on-time delivery, then show them the score.

6 min

Suppliers confirm ship dates when confirmation is part of the deal, not a favor you ask for. Write a confirm-by deadline into your PO terms, ask for a ship date on every line, make replying take one click or one line, require reconfirmation whenever the order changes, and score each supplier on acknowledgment and on-time delivery, then show them the score.

Morsa publishes this guide and appears in it. Every vendor fact was read on the vendor’s own site on 12 October 2026.

Why don’t suppliers confirm ship dates?

Mostly because nobody made it a requirement. In some buying systems, acknowledgment is optional unless the buyer asks for it. Coupa’s own supplier FAQ says of the PO acknowledgment field: “Some Coupa customers like their suppliers to use that field. Ask them if they want you to use it.” If the buyer never turns the requirement on, a supplier who skips it has broken no rule.

The second reason is that buyers ask for the wrong date. A PO usually carries a requested receipt date, the day you want the goods on your dock. The supplier controls the ship date. Microsoft’s Dynamics 365 documentation draws the line: “If any of your vendors don’t have specific delivery terms (such as delivery duty paid, delivery at place, or delivery at place unloaded), you must tell them when they should ship.” A supplier who confirms “your requested date” may be confirming a day it never planned to ship against.

The third reason is effort: if confirming means a login and a form per line, a busy supplier will answer the phone call instead.

What should your PO terms say?

Put these in the standard terms printed on, or linked from, every PO, and in each supplier agreement:

  1. A confirm-by deadline. Acknowledge each PO within a set number of business days. AT&S tells suppliers in a training guide hosted on SAP’s support site that it “needs an Order confirmation within three working days after receipt of the purchase order.”

  2. A ship date per line, not only a delivery date. Ask for both, at line level, so partial and split shipments are visible.

  3. Accept, change or reject, explicitly. The supplier either accepts the line as issued or proposes a new date, quantity or price, with a reason.

  4. Reconfirm on change. Any change by either side reopens confirmation.

  5. Notice of slips. The supplier tells you as soon as a confirmed date will move, within a set time of knowing.

  6. A realistic request date. NAED’s best-practice guide for electrical distributors and manufacturers says the default request date “should be an accurate estimate of historical lead time rather than ASAP, today’s date, or tomorrow.” Suppliers ignore dates they know are fiction.

How do you make confirming easy for suppliers?

Meet them where they already work, and keep the answer to one action. Both big supplier networks are free for suppliers: SAP Business Network’s standard account lists “Document collaboration on orders, invoices, order confirmations, ship notices, order change requests” at “Price: Free,” and Coupa says its portal “is completely free for suppliers.” In SAP’s one-time password setup, interactive email orders let suppliers “confirm and invoice purchase orders, without having to register,” though SAP says that setup “isn’t available for new customers.” For suppliers with many lines, Coupa’s CSV loader takes a “Promise Date” column, “The delivery date you are committing to for the goods.”

For suppliers who will never use a portal, an email with one structured question works: PO, line, quantity, need date, and “reply CONFIRM with your ship date.” Leverage AI builds its product on this, embedding POs “right in their inboxes,” and SourceDay offers “’No login’, interactive emails.” The test is simple: can a supplier’s customer service rep confirm a line from a phone in under a minute?

How should your system enforce confirmation?

Turn on the rules your ERP or network already has. In SAP Business Network, buyers can enable “Require delivery dates for order confirmations and ship notices.” In Coupa, buyers can make the promised date a confirmable field, and “If the dates differ, the system triggers a reconfirmation to ensure the buyer and supplier remain aligned on the delivery schedule.” In Dynamics 365 Supply Chain Management, the “Supplier requested and confirmed shipment dates” feature (version 10.0.40 or later) calculates a requested ship date per line from the requested receipt date, lead time, transport days and the vendor ship calendar.

Then make the confirmed date the one planning uses. SourceDay’s advice: decide “which field represents current supplier reality,” because “Without clear ownership, multiple versions of the truth emerge.”

How do you measure suppliers on it?

Score what you asked for, and share it. NAED defines on-time delivery as “The number of lines received complete from the manufacturer by the requested date based on normal/historical lead times or a negotiated delivery date divided by the total lines ordered,” and tells distributors to “Advise your channel partner if their on-time delivery is adequate, if it needs improvement, or if it is unacceptable.”

Metric

How to count it

What it tells the supplier

Acknowledgment rate

PO lines confirmed within the deadline, divided by lines issued

Whether they follow your terms

Time to acknowledge

Business days from PO sent to confirmation

How fast you get a commitment

Confirmed-date accuracy

Lines received by the confirmed ship date plus transit, divided by lines received

Whether their dates mean anything

On-time delivery (NAED definition)

Lines received complete by the requested date, divided by lines ordered

How they perform against your need

Date changes per line

Supplier-initiated date changes, divided by open lines

How often their commitments move

SourceDay reports that Prairie Machine improved supplier PO acknowledgment by 41% and on-time delivery by 11% “in the first year alone” using SourceDay.

What can software automate?

The reminders, the reading of replies and the scorecard math, on every open line, every day. What software cannot do is write your terms or decide what happens to a supplier who ignores them; that stays with purchasing. SourceDay, Coupa and SAP collect confirmations through a portal and email; Leverage AI through email and document parsing; Microsoft’s Procurement Agent drafts follow-ups inside Dynamics 365; Didero and Morsa run agents on top of your systems, and Morsa also reads confirmations that arrive in chat or by phone. Compared on price, ERPs and go-live in the best PO expediting software for 2026; the trigger and reply mechanics are in how to automate supplier follow-up on open purchase orders.

What does a captured confirmation look like?

At J4S, a 120-person glass manufacturing plant, a material warning at Mon 21:10 became work for the purchasing head, due Tue 12:00, after Morsa found 3 open orders on Line 2 that depended on it. After a nudge at Tue 10:00 and an escalation at Tue 13:00 with 1,200 pieces of Friday dispatch at risk, the supplier’s answer arrived at Tue 15:20: delivery Wednesday. That confirmation did not stay in a chat. Morsa moved the due date and recorded who moved it and why, and the goods receipt at Wed 11:40 closed the item. Times are illustrative per the J4S story; this is manufacturing proof. Over its first four weeks, J4S went from about 30% to about 75% of roughly 900 commitments done on time.

Where does Morsa fit, and when is it the wrong choice?

Morsa fits when supplier confirmations arrive everywhere: email, Outlook, Gmail, Teams, WhatsApp, a phone call or any other channel the team runs on. It reads the reply in whatever channel it comes, matches it to the open order, updates the date within your rules, flags what the new date breaks, and holds the line open until the goods receipt. Sunil K Verma, Plant Head at J4S: “I used to spend the first hour of every morning reconstructing yesterday. Now the chasing happens in the WhatsApp groups my supervisors already use, whether or not I remember.”

Morsa is the wrong choice if you want every supplier confirming in one portal with built-in scorecards (SourceDay, Coupa or SAP), or a full procure-to-pay suite. Morsa does have a supplier portal, but a light one: suppliers get a link to a form for the confirmation and answer without a login, and Morsa also takes answers in whatever channel the supplier already uses. It is built and proven in manufacturing, now onboarding its first distributors. Book a demo: https://cal.com/morsa

Sources

  1. Coupa, Orders FAQ, Purchase Order Collaboration with Buyers, Promised Date as a Confirmable Field in Orders and Confirm Order Confirmations with CSV Files; Supply Chain Collaboration, read 12 October 2026, docs.coupa.com, coupa.com

  2. Microsoft Learn, Calculate requested ship dates for purchase orders, read 12 October 2026, learn.microsoft.com

  3. AT&S, Purchase Order Collaboration Supplier Training Guide, hosted on SAP Ariba support, read 12 October 2026, support.ariba.com

  4. SAP, SAP Business Network Supplier Account Pricing, Enabling Suppliers on SAP Business Network and support note KB0405418, read 12 October 2026, sap.com, help.sap.com, support.ariba.com

  5. National Association of Electrical Distributors, Recommended Best Practices: Supply Chain Scorecard: Performance Measures (2012), read 12 October 2026, PDF

  6. SourceDay, How to Improve Promise Date Accuracy in ERP (17 June 2026), Supplier Portal and homepage, read 12 October 2026, sourceday.com/blog, sourceday.com/supplier-portal

  7. Leverage AI, Purchase Order Automation, read 12 October 2026, tryleverage.ai

  8. Morsa, J4S customer story, read 12 October 2026, /customers/j4s

Changelog

  • 12 October 2026: first published.

KEEP READING

KEEP READING

KEEP READING

Related pages

GUIDE

GUIDE

GUIDE

Best PO Expediting Software (2026): 6 Tools Compared

For most manufacturers and distributors chasing open purchase orders, SourceDay is the pick: a supplier portal plus an Open Order Chaser agent, certified with Epicor, Infor, NetSuite and Acumatica. Pick Leverage AI if your suppliers will only answer email, Didero for AI agents across all of procurement, Coupa or SAP Ariba if you already run that suite, and Morsa if each late PO must be tied to the orders and customers it hits.

Read the page

›

GUIDE

GUIDE

GUIDE

How to Stop Chasing Suppliers for Delivery Dates

You stop chasing suppliers for delivery dates by getting the date committed when the PO is placed instead of asking for it later. Put a confirm-by date in your PO terms, give every open PO one owner, time follow-ups to the need date, ask for replies in a fixed format, escalate before the date with the impact stated, score suppliers on it, and close each PO only on receipt.

Read the page

›

GUIDE

GUIDE

GUIDE

How to Automate Supplier Follow-Up on Open Purchase Orders

To automate supplier follow-up on open purchase orders, define the PO conditions that trigger a message: no acknowledgment by the confirm-by date, a need date approaching with no confirmed ship date, a date already passed, or a supplier-proposed change. Send one structured question per PO line, match the reply to that line, write accepted dates back to the ERP, and route anything outside tolerance to a buyer.

Read the page

›

FAQs

FAQs

FAQs

Questions people ask

Questions people ask

Still have a question? A founder will answer.

01

How do you get suppliers to confirm ship dates?

Make confirmation part of the deal, not a favor you ask for. Write a confirm-by deadline into your PO terms, ask for a ship date on every line, make replying take one click or one line, require reconfirmation whenever the order changes, and score each supplier on acknowledgment and on-time delivery, then show them the score.

02

Why don't suppliers confirm ship dates?

Three reasons. Nobody made it a requirement: in some buying systems acknowledgment is optional unless the buyer asks for it. Buyers ask for the wrong date: a PO usually carries a requested receipt date, but the supplier controls the ship date, so a confirmation of "your requested date" may mean little. And effort: if confirming means a login and a form per line, a busy supplier will answer the phone call instead.

03

What should PO terms say about order confirmation?

Six things: a confirm-by deadline in business days, a ship date per line and not only a delivery date, an explicit accept, change or reject with a reason, reconfirmation whenever either side changes the order, notice as soon as a confirmed date will move, and a realistic request date. NAED's guide says the default request date "should be an accurate estimate of historical lead time rather than ASAP, today's date, or tomorrow."

04

How quickly should a supplier acknowledge a purchase order?

Within a set number of business days written into your PO terms. As one example, AT&S tells suppliers in a training guide hosted on SAP's support site that it "needs an Order confirmation within three working days after receipt of the purchase order." Then track time to acknowledge per supplier, in business days from PO sent to confirmation, so you see how fast each one gives you a commitment.

05

How do you make confirming easy for suppliers?

Keep the answer to one action, where they already work. SAP Business Network's standard account and the Coupa portal are both free for suppliers, and Coupa's CSV loader takes a "Promise Date" column for suppliers with many lines. For suppliers who will never use a portal, send an email with one structured question. The test: can a supplier's customer service rep confirm a line from a phone in under a minute?

06

How do you measure suppliers on confirming ship dates?

Score what you asked for, and share it. Track acknowledgment rate, time to acknowledge, confirmed-date accuracy, on-time delivery and date changes per line. NAED defines on-time delivery as lines received complete by the requested date divided by total lines ordered, and tells distributors to advise each supplier whether its on-time delivery is adequate, needs improvement or is unacceptable.

WHERE MORSA FITS

WHERE MORSA FITS

WHERE MORSA FITS

Find out where AI could make your plant more money.

Answer a few questions about your plant. We come back with a free Manufacturing AI Profitability Plan, and we tell you honestly if we are not the right fit.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.