Should cost model: the build-up, with a worked example
Should cost = material + labor + setup + machine time + overhead + outside processing + logistics + fair profit [1]
An estimate, not an audit of the supplier’s books. Art of Procurement quotes a CADDi executive: “Even if you have a rough idea of the four components, material cost, process cost, overhead, and profit, that’s probably enough to start your conversation” [1].
A machined steel bracket, lot of 500. Every rate below is an assumption of ours, including that the $60 machine rate does not already include overhead. Replace them with yours.
Cost element | How it is built | $ per part |
|---|---|---|
Material | 4.0 lb blank × $1.50 a lb, plus 5% scrap | 6.30 |
Operator labor | 6 minutes at $30 an hour | 3.00 |
Setup | 3 hours × $80 an hour ÷ 500 parts | 0.48 |
Machine time | 12 minutes at a $60 an hour machine rate | 12.00 |
Overhead | 15% of labor, setup and machine time | 2.32 |
Outside finishing | Anodizing, an assumed quote | 2.00 |
Packing and freight | Per part | 0.60 |
Fair profit | 10% of the cost above | 2.67 |
Should cost | 29.37 |
Cost before profit is 6.30 + 3.00 + 0.48 + 12.00 + 2.32 + 2.00 + 0.60 = $26.70. Profit is 10% of that, $2.67, so should cost is $29.37.
The supplier quotes $34.50. The gap is $34.50 - $29.37 = $5.13 a part, 17.5% over should cost, or $2,565 on 500 parts. Ask about the biggest line first, machine time. If the supplier’s cycle is 15 minutes and not 12, that is 3 minutes at $1 a minute, $3.00 of the gap, plus the overhead and margin on it. You now have a specific question, not a feeling.
Where the inputs come from
If you do not make the part, Art of Procurement’s template points to these sources [1]: commodity price indices and material specifications for material; process sheets and published labor statistics for labor; equipment specifications and your own engineering and operations colleagues for machine time and cycle time; industry benchmarks for overhead, typically a share of conversion cost; freight quotes for logistics. The sources read do not publish a standard cycle time or machine rate. Treat yours as a first guess and ask the supplier to correct it.
How to run a should cost analysis, step by step
Pick the parts. Roughly 20% of parts carry 80% of the spend. Model those, not the tail [1].
Build the model. Start with material, process, overhead and profit. Use material price indices, wage data and your own engineers’ cycle times [1].
Compare. Put the estimate against the quote and see which line holds the gap. A gap in material starts a different conversation from a gap in overhead [1].
Open the conversation. Share the model as a starting point and ask the supplier to correct it. Their corrections are the cost data you wanted [1].
Set targets over time. The gap rarely closes in one round; agree a path over several years if needed [1].
You can also run the analysis before the request for quotation, to have a benchmark for competing bids [2]. Use it as the benchmark, with one ask: “this is my estimate, where am I wrong?”
Who uses should cost analysis
Buyers and sourcing managers at manufacturers, to challenge quotes on machined, fabricated and molded parts. Cost engineers in larger plants. Distributors buying from manufacturers use it to test a price increase. In the example, material is $6.30 of $29.37. A 10% steel increase adds $0.63, or $0.69 with the 10% profit: 2.4% of the should cost, 2.0% of the $34.50 quote. A manufacturer asking for 8% needs to explain the rest.
Should cost model software: the tool categories
A spreadsheet. Enough for the top 20% of parts. The table above is one.
Should-cost software. A category that spans spend and cost analytics, CAD-based cost estimation, and platforms that build should-cost models at scale. CADDi, named by Art of Procurement, targets low-volume direct material parts [1]. Use it when you have thousands of parts and a drawing for each.
Your ERP’s costing and your quoting history. Past jobs already hold real routings and machine rates; see manufacturing quoting software.
Common should cost mistakes
Chasing precision. Accuracy matters less than what you do with the gap [1].
Leaving the profit out. A fair margin makes the rest of the model credible [1].
Double counting. A machine rate often already includes overhead. Check before adding an overhead line on top.
Modeling the tail. A $0.40 washer is not worth the hour.
Using it as a weapon. Share it as a question, not an attack [1].
Building the should cost from your own jobs
A should cost needs real routings, rates and prices. Morsa pulls them from your ERP and past jobs:
For a new drawing, it reads the part, finds similar past jobs, their routings, machine rates and the current material price, and builds the table above.
When the supplier’s quote arrives, it shows the gap line by line.
The buyer decides what to challenge; Morsa drafts the question to the supplier and sends it from the buyer’s mailbox once approved.
It is not a CAD-based costing platform; for thousands of drawings, use that category. To see it on your parts, book a 30-minute walkthrough.
Related terms
Operations glossary: every term.
Supplier performance management: scoring suppliers once you buy.
MOQ: the minimum that shapes the piece price.
ABC analysis: how to pick the parts worth modeling.
Lead time: the other part of a supplier’s quote.
Sources
Art of Procurement, Should-Cost Analysis: My Guide for Procurement (27 August 2026): https://artofprocurement.com/blog/should-cost-analysis-my-guide-for-procurement (read 12 November 2026)
Fairmarkit, Should-Cost Analysis: https://www.fairmarkit.com/glossary/should-cost-analysis (read 12 November 2026)
ControlHub, How to Build a Should Cost Model: https://www.controlhub.com/blog/should-cost-model (read 12 November 2026)