Kitting in a warehouse and on an assembly line
In a warehouse, kitting combines several items into one package that ships as a single SKU, such as a computer, mouse and headset sold as a starter pack. Kits are usually built to stock ahead of orders and sometimes built to order as orders arrive [1]. The system keeps a kit bill of materials (BOM), the list of what goes in, and uses up the component stock as each kit is built [1].
On an assembly line, kitting gathers the exact parts for a job into a bin, tote or pre-built sub-assembly and delivers it to the operator, so nobody walks the stockroom or hunts for a part [2]. UNEX, a vendor of workstations, describes a manufacturer that pre-assembles engine modules at a side station and delivers them to the main line as a kit [2].
A worked example: when kitting pays
A distributor sells a 5-item starter set and ships 2,000 a month. Handling times are our estimate: 30 seconds a pick, and 90 seconds to build a kit, which includes a kitter batch-picking its 5 parts to a packing table.
Measure | Pick 5 items per order | Pick 1 kit per order |
|---|---|---|
Picks per order | 5 | 1 |
Pick time per order | 150 s | 30 s |
Kit build per kit | 0 | 90 s |
Labor per order | 150 s | 120 s |
Labor hours for 2,000 orders | 83.3 | 66.7 |
SKUs to manage | 5 | 6 (5 parts plus the kit) |
The 2,000 orders take 150 × 2,000 ÷ 3,600 = 83.3 hours without kitting and 120 × 2,000 ÷ 3,600 = 66.7 hours with it, 16.7 hours saved, or 20%. At $20 an hour (our estimate) that is about $333 a month. The break-even is a kit build under 150 - 30 = 120 seconds; above that, kitting costs more labor than picking. The saving is small; the case usually rests on fewer wrong picks, a faster pack station, or a line that stops when a part is missing.
How to kit for a customer’s line
Agree the kit list (kit BOM) and the release trigger with the customer.
Set the lead time from release to delivery.
Pick each kit’s parts into a tote and verify every part by scan before it leaves.
Label by job and station, and count what is left over.
Agree who owns the stock and who pays for a short part.
For price: the survey average is $10.79 an hour [4]. In our example, 120 seconds of labor is 120 ÷ 3,600 × $20 = $0.67 a kit, and a per-kit fee has to cover that plus space and margin.
Kitting vs assembly
Kitting | Assembly | |
|---|---|---|
What happens | Items are grouped and stay unchanged | Parts are joined, configured or tested into a new product [3] |
What happens to the parts | They stay intact and can be taken out [3] | They change identity and are tracked as a finished good [3] |
What it needs | A packing table and a short training [3] | Trained assemblers, fixtures, a bill of materials and work orders [3] |
Kitting and assembly are often sold together as “kitting and assembly services”, but they are different jobs [1][3].
Kitting services and what they cost
A 3PL kitting service builds kits from your components and stores or ships them. In The Fulfillment Advisor’s 2026 survey the average kitting fee was $10.79 an hour, and subscription box fulfillment ran $2.50 to $5.00 an order where offered [4]. Other providers publish higher figures; see 3PL pricing. Price your own kit by the unit before you sign.
When to kit
Kit when items are sold or built together, when orders have many lines, when a station has more parts than it can hold, or when a missing part keeps stopping the job. Do not kit slow, rarely sold combinations: every kit is another SKU to count and keep. Kits built to stock only pay if you sell them, so build-to-order kits suit variable demand; see make to order vs make to stock. Review which parts to kit first with ABC analysis.
Common kitting mistakes
Kitting a slow combination. The kit sits, and the components are tied up. Kit what sells.
Short kits. A kit missing one part stops the job anyway. Verify by scan before it leaves the kitting area.
No kit BOM. Without a list of what is in the kit, the system cannot use up component stock [1].
Ignoring build time. Measure the kit build; above the break-even in the example, picking is cheaper.
Calling assembly kitting. If parts must be joined or tested, plan for assembly labor and tools [3].
Making sure every kit is complete
Before a kit is built:
For each work order released in your ERP over the next few days, it checks every kit component against stock and open purchase orders.
For a short part, it shows the jobs blocked and, under a rule the buyer approved, asks the supplier for a date.
It tells the kitter in Teams which kits are complete and which are on hold, and a person approves any change to the job.
JRG Automotive, a Morsa customer, caught 5 of 8 production-stopping shortages early enough to act, about $2 million saved. To see it on your jobs, book a 30-minute walkthrough.
Related terms
Operations glossary: every term.
Pick and pack: the step kitting shortens.
ABC analysis: which items are worth kitting.
Make to order vs make to stock: build kits ahead or when ordered.
Sources
Infios, Kitting and assembly: https://www.infios.com/en/knowledge-center/glossary/wms-kitting-and-assembly (read 12 November 2026)
UNEX, The Role of Kitting in Lean Manufacturing (a vendor of workstations): https://blog.unex.com/the-role-of-kitting-in-lean-manufacturing (read 12 November 2026)
Racklify, Product Assembly vs Kitting: Key Differences For Warehouses: https://racklify.com/encyclopedia/product-assembly-vs-kitting-key-differences-for-warehouses/ (read 12 November 2026)
The Fulfillment Advisor, 2026 Warehousing and Fulfillment Costs and Pricing Survey: https://www.thefulfillmentadvisor.com/2026-warehouse-costs-and-pricing-survey/ (read 12 November 2026)