Production planning process: 8 steps from demand to dispatch, with a worked week

The production planning process runs in 8 steps: review demand, agree the monthly sales and operations plan, set the master production schedule, run MRP (material requirements planning) for materials, check capacity, schedule the work, release it to the floor, and feed back what actually happened. It runs on three clocks: monthly for volume, weekly for what to build and buy (with next week frozen), and daily for what starts today and whether its parts are on hand. At a 120-person plant, one planner and the production manager usually run it, with one or two buyers (our estimate).

8 min

Morsa publishes this guide. Morsa is software with an AI agent that works in your ERP, email and Teams; it checks each work order’s parts before release and chases short ones, with a planner approving.

Quick answer

  • The step never to skip: the capacity check. MRP plans material, not machine hours: Business Central’s documentation says its planning entries “assume infinite capacity” [1].

  • The rule that holds the plan together: freeze next week. Changes inside it need the production manager’s yes.

  • How to promise a date: the first week after the frozen week where material and capacity are both clear, plus assembly and test time.

The 8 steps, with what goes in and what comes out

Step

Input

Output

1. Review demand

Open customer orders, forecast, finished-goods stock

Demand by item by week, 8 to 12 weeks out

2. Sales and operations planning (S&OP)

Sales outlook, capacity, inventory targets, budget

Volume by product family by month, agreed by sales, operations and finance

3. Master production schedule (MPS)

Weekly demand, stock, the S&OP volume

Which end items, how many, in which week

4. Material requirements planning (MRP)

MPS, bills of materials, stock, open purchase orders (POs), lead times

Planned POs and work orders, plus MRP’s suggested actions, such as “move this PO earlier”

5. Capacity check

Planned work orders, routings, hours per work center

Load by work center by week, every overload resolved

6. Scheduling

Work orders, machine hours, material arrival dates

The sequence for each machine, shift by shift

7. Release and dispatch

The schedule, a parts check, tooling and people

Released work orders with kits pulled

8. Feedback

Completions, scrap, downtime, receipts

ERP status up to date, each miss with its reason

MRP inside NetSuite, Business Central and other ERPs: MRP in your ERP.

An overload in step 5 has five fixes: overtime, moving a job to a week with room, an alternate machine, outsourcing, or a new promise date. Pick the cheapest and say who agreed. For finite scheduling in step 6, see advanced planning and scheduling.

Who does each step

Step

Under 100 people

100 to 300 people

Demand and S&OP

Owner or GM, with the production manager

GM chairs; sales, planning and finance bring numbers

MPS and MRP

Production manager

One planner at about 120; a master scheduler by 300

Buying and expediting

Production manager or one buyer

One or two buyers at 120; two or three, split by commodity, by 300

Capacity and scheduling

Production manager

The planner for the week; the production manager or area leads for the day

Release, dispatch, feedback

Supervisor and stores

Supervisors and stores, plus a material handler per area by 300

Our estimates. Plans break at handoffs, so write each one down.

The rhythm: monthly, weekly, daily

Ours, not a standard:

When

What

Who

Monthly

S&OP review, 60 to 90 minutes, by product family

GM, sales, planner, finance

Monday morning

Review demand, update the MPS, run MRP (2 to 3 hours)

Planner

Monday afternoon

Capacity check; buyers place POs and act on MRP’s suggested actions

Planner, buyers, production manager

Thursday

Freeze next week; send the kit list to stores

Planner, stores

Every morning

15-minute plan against actual (manufacturing KPI dashboard)

Production manager, supervisors, planner

Promising a date on a new order

In make to order, promise the first week that passes three checks, in this order:

  1. Outside the frozen week, unless it goes through the exception below.

  2. Material: every part on hand, on a supplier-confirmed PO that lands in time, or orderable within its lead time.

  3. Capacity: the bottleneck work center has the hours, after the moves you are willing to make.

Add assembly, test and shipping days and promise that date, not the one asked for. This is the make-to-order core; in make to stock the forecast drives the MPS instead, and in engineer to order engineering release comes before MRP.

The frozen-week exception. For a rush order that must start inside the frozen week, the planner shows what it bumps: which job, whose order, how many hours, what overtime costs. The production manager decides that day; on a yes, the bumped customer gets a new date the same day. Say no when the parts are not on hand.

A worked week: one rush order, from promise to dispatch

A 120-person plant makes hydraulic valves. On Monday of week 1 a customer asks for 200 VA-40s, ideally by Friday of week 2. Each needs a machined body, two seal kits and a solenoid. Each of the two mills has 40 hours a week.

When

Step

What happened

Week 1, Monday

1 and 3: demand, MPS

40 in stock: net need 160. Week 1 is frozen, so bodies go in week 2

Week 1, Monday

4: MRP

Seal kits: 400 on hand, 320 needed. Solenoids: 50 on hand plus 100 on a PO due in week 2: 10 short. A new PO at the 15-working-day lead time lands Monday of week 4, too late

Week 1, Monday

5: capacity

160 bodies at 9 minutes is 24 hours. Week 2 already holds 62 of the mills’ 80 hours: 86 hours, 108%. The planner moves a 10-hour stock job to week 3: 76 hours, 95%

Week 1, Tuesday

4: expedite

The buyer asks the supplier to add 10 to the open PO; it confirms 110 for Thursday of week 2

Week 1, Tuesday

Promise

Parts are ready Thursday of week 2, so assembly starts Monday of week 3; two days of assembly and a day for test: promise Friday of week 3. Friday of week 2 would need machining in frozen week 1 and solenoids before Thursday, so it is not offered

Week 1, Thursday

6: schedule

Bodies on mills 1 and 2, Tuesday and Wednesday of week 2, 12 hours each; assembly Monday and Tuesday of week 3

Week 3, Monday

7: release

160 bodies, 320 seal kits and 160 solenoids on hand. Assembly released

Week 3, Tuesday

8: feedback

3 of 160 fail the leak test, reworked Wednesday; that rate becomes the next order’s scrap allowance

Week 3, Friday

Shipped

200 ship on the promised date

Starting from a spreadsheet and your ERP

Set up one sheet with these columns: work order, item, quantity, customer order, promise date, work center, hours, planned week, short part, PO number, supplier-confirmed date, status. Add a load tab with one line per work center per week: available hours, planned hours, load %.

The first weekly review takes about an hour (our estimate):

  1. Last week’s misses, each with its reason.

  2. Load per work center for two weeks, overloads resolved.

  3. Open PO lines due in two weeks with no confirmed date, each with a chaser.

  4. Freeze next week.

When ERP lead times and routings are wrong, fix the ones that hurt first: set lead times for the 20 parts on the most orders from their last three receipts, time five jobs on each bottleneck work center and correct its routing hours, then re-run MRP.

6 metrics for a production planner

Metric

Formula

What it tells you

Schedule attainment

Operations finished by their scheduled date ÷ operations scheduled

The floor followed the schedule

On-time delivery

Order lines shipped in full by the promise date ÷ lines due

Customers got what you promised

Capacity load

Planned hours ÷ available hours, per work center per week

Over 100% means a late order

Shortages at release

Work orders that could not start for a missing part ÷ work orders due to start

What MRP and buying missed

Unconfirmed PO lines

Open PO lines with no supplier-confirmed date ÷ open PO lines

How much of the plan is a guess

Frozen-week changes

MPS lines changed inside the frozen week ÷ MPS lines that week

Whether the floor can trust the plan

Set targets against your own last 13 weeks; watch the trend more than the level.

Why production plans fail

Beyond a skipped capacity check and unconfirmed supplier dates:

  1. No frozen window. The plan changes daily, so the floor runs what is easiest.

  2. Feedback entered late. The ERP shows work that is done or scrapped, and the next MRP run is wrong.

  3. Planning to a speed the line has never reached. If the line has never beaten 80 parts an hour, a plan at 100 is late before the week starts.

  4. The plan lives in one person’s spreadsheet. It works until that person is out; production planning software compares ERP modules, scheduling tools and spreadsheets, and when to move off one.

Catching the short part before release

Each morning, Morsa checks every work order due to start against stock and supplier dates in your ERP, whether JobBOSS2, Epicor, Global Shop or NetSuite.

  1. When a part will be short, it shows the orders it hits and asks the supplier for a date from the buyer’s mailbox. The buyer approves each kind of message once; after that it runs under that rule.

  2. It proposes a new sequence; once the planner approves, it updates the ERP and tells the supervisor in Teams.

JRG Automotive, a Morsa customer, caught 5 of 8 production-stopping shortages early enough to act, about $2 million saved. Book a 30-minute walkthrough.

What to do this week

  1. Write the 8 steps on one page with a name beside each.

  2. Freeze next week from Thursday.

  3. Run a capacity check on next week for your two busiest work centers.

  4. Count open PO lines due in two weeks with no confirmed date; chase those behind customer orders first.

The production schedule template has these columns and the load tab built, with the worked week filled in.

Sources

  1. Microsoft Learn, Run full planning, MPS, or MRP (Business Central): “Business Central generates worksheet entries that assume infinite capacity”: https://learn.microsoft.com/en-us/dynamics365/business-central/production-how-to-run-mps-and-mrp (read 8 November 2026)

  2. Encyclopedia of Management, Production planning and scheduling (via Encyclopedia.com): https://www.encyclopedia.com/management/encyclopedias-almanacs-transcripts-and-maps/production-planning-and-scheduling (read 8 November 2026)

Keep reading

Keep reading

Keep reading

Related pages

Guide

Guide

Guide

Production planning software: what it does, which kind you need, and 15 tools compared

Production planning software decides what a plant will make, in what order, on which machines, and with which materials, over a horizon from the next shift to the next quarter. It comes in three forms: the planning module inside an ERP, a standalone advanced planning and scheduling (APS) tool, and the spreadsheet most plants actually run on. The best pick in 2026 is Morsa on top of whichever of the three you run, because Morsa keeps the plan true after it changes.

Read the page

›

Guide

Guide

Guide

Advanced planning and scheduling (APS): what it is, what it costs, and when it beats Excel

Advanced planning and scheduling (APS) software puts every operation on a machine and a time slot without loading any machine past its hours, and re-sequences the rest when something changes. Published prices run from €199 a month (SkyPlanner) to $25,000 once (EDGEBIC); for a 40-machine shop that is about €10,800 a year or $25,000 once, before implementation.

Read the page

›

Guide

Guide

Guide

NetSuite MRP: how to set it up and run it, and where MRP lives in other ERPs

In NetSuite, MRP (material requirements planning) runs inside Supply Planning. You turn on the Advanced Inventory Management and Material Requirements Planning features, set each item's replenishment method, lead time, safety stock and lot size, run a supply plan, and release its planned orders from the Supply Planning Workbench. Oracle says MRP is part of its Demand Planning module, so first check that module is on your contract. NetSuite plans at infinite capacity: it plans material, not machine hours.

Read the page

›

FAQs

FAQs

FAQs

Questions people ask

Questions people ask

Still have a question? A founder will answer.

01

What is production planning and control?

Planning is steps 1 to 6: what to make, when and with what. Control is steps 7 and 8: release, then actual against plan.

02

What is the difference between production planning and scheduling?

Planning sets quantities by week; scheduling sets the job order on each machine by shift.

03

Can you run the production planning process in Excel?

Yes, under about 100 people with one planner and a stable mix, using the production planning template columns above. It breaks once two people edit it.

04

What does a production planner do each day?

Checks yesterday against plan, clears today's shortages before release and moves jobs when something breaks.

05

How far ahead should a plant plan?

Volume six to eighteen months out [2], the MPS 8 to 12 weeks, the schedule one to two.

Where Morsa fits

Where Morsa fits

Where Morsa fits

Find out where AI could make your plant more money.

Answer a few questions about your plant. We come back with a free Manufacturing AI Profitability Plan, and we tell you honestly if we are not the right fit.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions

© 2026 Lunar Inc. All Rights Reserved.

Machines, people, and vendors, finally in one. We start with yours.

For queries, feedback or suggestions